The three main activities happening in Cyclops are below. Most of the work is happening more or less in parallel.

Cyclops Respin Activities

  • Software development
    • Sccb interface to camera module is currently working
    • Obtain an image from camera module to show the board is completely working
    • Integrate new camera module driver into current code stack
  • Optics for new camera module
    • Create a spreadsheet with 5 or 10 candidate lens setups. Discuss options with Mohammad
    • Narrow field down to 2 to 4 and order
    • Test lens in lab in various deployment conditions
  • Board fix and refabrication
    • Four areas of interest to redesign
      • 51-pin connector is wired incorrectly
      • 22-pin camera connector is wired backwards
      • Vcc and GND planes are shorted through a screw hole
      • Possibly change lens mounting hole locations
    • Contact original layout company to see what they say about their mistakes
      • Screw hole short is only mistake that is clearly their fault alone
    • Decide who will redesign the board (Johnathan?)
    • Wait until we can get an image before actually getting the refab done
    • Order 4 boards fabbed, 2 assembled for extensive testing in lab
    • Once we are sure the refab works, get all 100 ordered

Tech Report

  • Outline of tech report done by Monday (Aug 6). Meet with Mohammad to review.

Pitfall Trap Planning Activities

  • Run Tenet on MicaZs in lab, look at code
  • Visit JR with Tenet developer
    • Planned for Wednesday, Aug 15
  • Flesh out details for deployment plans

External Flash Storage Activities

  • What software already exists that we can leverage?